Sr.No | Client | Project | Work Description | Job Period |
---|---|---|---|---|
1 | Larsen & Toubro Ltd. ECC Division, Chennai |
TWAD Vellore Package-1 | Pipe Coal Tar Coating & Painting works.1,38,000SQM Up to 1500 mm Dia | 2013 |
2 | Reliance Industries. Dahaej.Gujarat. |
PET-3. Dahej | Pipe Coal Tar Coating & Painting works by Semiautomatic Plant. Up to 1500 mm Dia Qty:15637 SQM |
2012 |
3 | Larsen & Toubro Ltd. Hydrocarbon Mid&Downstream. Vadodara. |
IOCL Paradeep Refinery. | Flu Gas Ducting & Refractory support works. 4000 x 30/ 40 thk | 2011-12 |
4 | Larsen & Toubro Ltd. ECC Division, Bangalore |
Hogennakal Water Supply Project. Krishnagiri. Tamilnadu | Pipe Coal Tar Enamel Coating on MS Pipeline Up to 15000 Dia. 160000 Sq.Mtrs | 2011-12 |
5 | Larsen & Toubro Ltd. ECC Division |
448 MW Konaseema Power Plant. Ravulapalem. A.P. | Erection of HRSG Modules,Stack,Boiler Drums &Piping. (IBR&Non IBR) Fabrication & Erection of structural steel for STG ,GTG & HRSG. | 2005-2006 |
6 | Larsen & Toubro Ltd. ECC Division |
90 MW CCP POWER PLANT. I.P.C.L.Dahej. | Fab&Erection of M.S.Cone roof Tanks, Fab&Erection of Structural Steel and Piping. | 1998 - 1999. |
7 | RELIANCE INDUSTRIES LTD. | RELIANCE PETROLIUM LTD. JAMNAGAR | Fab&Erection of Structural Steel, Installing of Chemical Anchors &Miscellaneous works. | 1998 - 1999 |
8 | Modren Petrofils. Por.Baroda. | D.G.Power House | Fabrication&Erection alignment and welding of 51 Mtr height Chimney | Dec.2001. |